Kinerja Mobilisasi Bahan Dan Peralatan Pada Pekerjaan Konstruksi

Studi Kasus Pembangunan Jalur Kereta Api Lintas Makassar-Parepare

Authors

  • Andi Sri Rezeky Aprillia S Program Studi Teknik Sipil Fakultas Teknik Universitas Bosowa
  • Ahmad Yauri Yunus Program Studi Teknik Sipil Fakultas Teknik Universitas Bosowa
  • Savitri Prasandi Mulyani Program Studi Teknik Sipil Fakultas Teknik Universitas Bosowa

Keywords:

Mobilization Performance, Mobilization Advantages, Mobilization Weaknesses, Material and Equipment Mobilization

Abstract

The purpose of this study was to analyze the effect of the performance of the mobilization of materials and equipment, the advantages of mobilizing materials and equipment and the weaknesses of the mobilization of materials and equipment on the mobilization of materials and equipment and to determine the most influential variables. This study uses quantitative methods with the number of respondents as many as 55 people. The instrument testing uses validity and reliability tests, while the data analysis method uses multiple linear regression with the F test and t test. The results showed that the variables of Material and Equipment Mobilization Performance (X1), Excess Mobilization of Materials and Equipment (X2) and Weaknesses of Materials and Equipment (X3) simultaneously affected the Mobilization of Materials and Equipment Equipment (Y), Based on the t-test, the variable Performance Mobilization of Materials and Equipment (X1), Advantages of Mobilization of Materials and Equipment (X2), and Weaknesses of Mobilization of Materials and Equipment (X3) have a positive and significant effect on Mobilization of Materials and Equipment (Y). and the value of Adjusted R Square which means the influence of the independent variable on the dependent variable is 71.4%.

References

Asnudin, Andi. 2005. “Manajemen Proyek”. Palu: UNTAD Press.

Bastian. 2001. “Pengaruh Kompensasi, Motivasi Karyawan, dan Komitmen Organisasi Terhadap Kinerja Karyawan”. Jurnal Akuntansi: Vol 9 No 2 (2017). https://journal.maranatha.edu/index.php/jam/article/view/4 80, diakses 4 Agustus 2021.

Dipohusodo, Istimawan. 1995. “Manajemen Proyek & Konstruksi Jilid 1”. Yogyakarta : Badan Penerbit Kanisius.

Dipohusodo, Istimawan.1996. “Manajemen Proyek & Konstruksi.Kanisius”. Jogjakarta.Psychiological Bulletine. Vol. 97

Ervianto (2002) “ Pengertian Proyek Kontruksi “ dari http://e-journal.uajy.ac.id/4367/3/2MTS01738.pdf

Gould, 2002, dan Eka Dannyanti, 2010 “ Pengertian Proyek Konstruksi “ dari http://e-journal.uajy.ac.id/4367/3/2MTS01738.pdf

Kementrian Pekerjaan Umum Perumahan Rakyat , 2017, Permen PUPR, Tentang Pengendalian Pengawasan Pada Persiapan Pelaksanaan Pekerjaan Konstruksi.

Manullang. 1996. “Dasar-dasar Manajemen”, Jakarta : Ghalia Indonesia. Martoyo,

Mangkunegara Prabu Anwar 2005. “Manajemen Sumber daya Manusia Perusahaan”. Bandung : PT Remaja Rosdakarya.

Marwansyah. 2015. “Manajemen Sumber Daya Manusia”, Jakarta

Mangkunegara Prabu Anwar. 2000. “Manajemen Sumber Daya Manusia”, Bandung. PT, Remaja Rosdakarya.

Notoatmodjo, Soekidjo, 2003, “Pengembangan Sumber Daya Manusia”, Jakarta: PT. Rineka Cipta

Robbins, Stephen P. 2001. “Perilaku Organisasi: Konsep, Kontroversi, Aplikasi, Jilid 1, Edisi 8, Prenhallindo”, Jakarta

Susilo. 1987. “Manajemen Sumber Daya Manusia”, BPFE, Yogyakarta..

Satori, Djam’an dan Komariah, Aan. 2012. Metodologi Penelitian Kualitatif. Bandung: Alfabeta.

Sugiyono, 2006. Metode Penelitian Kuantitatif, Kualitatif, dan Kombinasi, Bandung: PT Remaja Rosdakarya,

Siregar, Syofian. 2011. Statistika Deskriptif untuk Penelitian: Dilengkapi Perhitungan Manual dan Aplikasi SPSS Versi 17. Jakarta: Rajawali.

Sugiyono. 2013. Metode Penelitian Kuantitatif, Kualitatif, dan R&D. Bandung: CV Alfabeta.

Rivai, 2013:604. “Kinerja” dari (http://repository.umy.ac.id)

Downloads

Published

2023-01-10